How to Finish Flooring During Summer Break

Summer is the one long window for school flooring work. Plan backward from the first day so the floor is down, settled, and aired out in time.

Key takeaways

  • Check the lead time on each product page before you set dates
  • Large rubber orders can need extra processing time
  • Let rolls and sheets relax or acclimate before you cut them
  • Leave days at the end to air out new rubber
The first day of school is the deadline. Plan every step back from it.

Plan backward from the first day

A summer job has a fixed end date, so build the schedule in reverse. Each step needs its own block of time, and a late step pushes every step after it.

  • 1. Samples: order free samples and approve the product.
  • 2. Order: place the order early enough to cover the lead time.
  • 3. Delivery: book the delivery for a day when staff can receive it.
  • 4. Settle: let the material relax or acclimate in the room.
  • 5. Install: install, then clean the floor.
  • 6. Air out: ventilate the rooms before students return.

Order early

Every product page shows the lead time when you select a color and a size. Use that number to set your order date. The Rubber Gym Rolls page notes that orders over 1,000 sq. ft. may need extra processing time before they ship.

Choose Quick Ship Pre-Cut rubber if…Choose custom-cut rubber if…
The install date is in the next two weeksThe job is more than three or four weeks out
A launch-palette color works for the roomYou need a color outside the launch palette
Standard lengths (10, 15, 25, 50 ft) fit the spaceYou need a specific length to avoid seams
Working toward a summer deadline?

Give us your install dates and we will plan the order and delivery around them.

Leave time for the floor to settle

The Rubber Gym Rolls installation guide says to loose lay the rolls and let them relax for 24–48 hours before you cut them. Our Quick Ship post tells home-gym buyers to let a roll relax overnight. For sheet vinyl, our buying guide says to let the sheet acclimate for 24 hours before you cut it.

⚠️ Our pages give different relax times for rubber rolls. Follow the installation instructions for the exact product you buy.

Air out before students return

New rubber has a stronger smell that fades over time. Air out new mats in a well-ventilated area with open windows or fans. A few days is ideal, but even a few hours can help.