Split the gym into phases
A gym that stays open cannot close every zone at once. Divide the work into phases that follow your zones, for example cardio first, then free weights, then the functional area. Keep one area open for each type of training while another area is closed. Tell members which zone closes on which dates, so they can plan their training.
Stage the deliveries
A phased job does not need all the rubber on day one. Material that arrives too early can block the site and get moved twice. FlooringInc can sync delivery to a phased schedule, across several truckloads, with warehouse staging for the days the site cannot receive.
Keep color the same across phases
The color of the same roll can vary between separate orders. For the best match, order the rolls for every phase at the same time, and ask for staged delivery of the later phases. Rolls can also be directional. If two rolls do not match, flip one roll or turn it 180 degrees.
Share your phases and dates. We can quote one order with staged deliveries.
Install method for each phase
| Method | What it means for a phased job |
|---|---|
| Loose lay | The easiest method. You lay the rubber with no adhesive, and you can adjust or remove it later. |
| Double-sided tape | Tape goes on the subfloor along the perimeter of each roll. The floor stays more stable and you can still remove it. |
| Adhesive | A permanent bond for high-traffic gym floors. The adhesive needs time to cure before the zone opens again. |
Time each phase needs
- Relax: lay the rolls loose in the zone for 24 to 48 hours before you cut them, as the Rubber Gym Rolls page says.
- Cut: use a straight edge and a utility knife with a fresh blade. At the walls, leave a gap about as wide as the roll is thick.
- Glue in sections: spread the adhesive no more than 10 feet at a time, and unroll the floor into it.
- Press: roll glued rolls with a 100-pound roller. If you do not have one, walk on the floor in small, choppy steps.
- Cure: wait at least 24 to 48 hours before heavy equipment goes on a glued floor.
- Check: look for gaps, loose spots and lifted edges before members use the zone again.